Premium Plate’s New Axis Facility: Construction Progress and Next Steps
Construction of Premium Plate’s new steel processing facility in Axis, Alabama, continues to advance, with major equipment installation underway and several building and infrastructure milestones approaching completion.
As of early November 2026, work is progressing on the building’s exterior, office interiors, and rail connection. The project remains on schedule, with construction expected to finish by the end of December and the facility set to open in January 2027.
Located at 217 Salco Road in Mobile County, the new facility represents an investment of more than $20 million in infrastructure and equipment. The purpose-built location will provide Premium Plate, a TF Warren company, with additional steel processing capacity and a permanent operating site in the region.
Building Construction and Interior Work
One of the upcoming construction milestones is completing the building's exterior enclosure. The structure is expected to be fully dried in during the first half of November, meaning the roof and exterior building envelope will provide protection from weather exposure.
This stage is particularly relevant to the remaining interior work, as it allows construction activities to continue in a more protected environment.
Work inside the office area is already underway, with drywall installation scheduled to begin during the second week of November. These improvements are progressing alongside work in the main production area, where installation of the facility’s new processing equipment has started.

New Steel Processing Equipment Installation Underway
Installation of three major equipment systems began during the first week of November 2026. The new facility will include laser cutting equipment, a blasting system, and a paint booth.
Each system serves a distinct purpose in industrial steel processing:
- Laser cutting equipment: Enables precise cutting of steel plate into specified shapes and dimensions.
- Blasting equipment: Supports steel surface preparation by removing surface contaminants and preparing material for further processing or coating.
- Paint booth: Provides a controlled environment for applying protective coatings to steel components.
The addition of these systems is central to Premium Plate’s plans to expand its processing capabilities. Bringing cutting, surface preparation, and coating equipment into the new facility will provide the infrastructure needed to support a broader range of steel processing requirements.
Rail Spur Nears Completion
Another significant development is the rail spur serving the Axis facility, which is scheduled for completion in early November.
Rail infrastructure is particularly useful in the steel industry because of the size and weight of materials involved. It provides an alternative to road transportation for suitable shipments and can support the movement of substantial quantities of steel.
The new rail connection will form part of the site's transportation infrastructure, complementing the facility's processing and material-handling operations.
A Permanent Facility in Mobile County
The Axis project marks a transition in Premium Plate’s operations in Mobile County. The company previously operated from leased facilities in the region, including a location along Highway 43 and its current facility in Chickasaw.
Unlike these leased locations, the new facility is being developed specifically for Premium Plate's long-term operational requirements.
Premium Plate supplies mill-certified steel plate and structural steel products to industries including construction, oil and gas, power generation, pressure vessel manufacturing, marine, transportation, and tank manufacturing.
The new facility is intended to provide additional capacity to support these markets while improving the efficiency of steel processing operations.
Beyond the investment in buildings and equipment, the project is expected to create 12 new jobs over the next two years, contributing to the manufacturing workforce in Mobile County.

Next Steps and Expected Opening
The remaining construction schedule includes completing the building enclosure, continuing office interior work, finalizing the rail spur, and progressing with the installation of new processing equipment.
Construction is scheduled to be completed by the end of December 2026, with the opening of the new Axis facility still on track for January 2027.
Once operational, the new facility will establish Premium Plate's permanent steel processing presence in Axis, with expanded capacity for services including cutting, blasting, painting, beveling, and rolling.
About the author

Chad Odom is a seasoned steel industry professional with over 20 years of experience in steel service center operations, sales, and management. Beginning his career in 2004 in warehouse operations at O’Neal Steel, he advanced into inside sales before transitioning into leadership roles, including Sales Manager at Premium Plate and Operations Manager at Total Plate. Since 2025, Chad has served as General Manager of Premium Plate, based in Mobile, Alabama. His extensive industry expertise includes steel procurement, project management, estimating, plate processing, fabrication, shop production, strategic sales, and customer relationship management. With a comprehensive understanding of the steel service center industry, from warehouse operations to executive leadership, Chad brings a hands-on, solutions-driven approach to operational efficiency, customer satisfaction, and business growth.
View all postsRecent Posts

Steel Plate Supplier Selection Criteria: 10 Questions to Ask

The Importance of Proper Refinery and Petrochemical Maintenance

Premium Plate Plans $20M Mobile County Facility

What Is Marine Steel Plate and How Is It Used in Vessel & Barge Repair?